Churchill train and port.

Train service to Churchill has been suspended for over a year. Claude Daudet photo.

If money becomes available, Hudson Bay Railway could begin repairing the damaged tracks between Churchill and Gillam as early as September according to HBR President Sergio Sabatini. He confirmed with the Canadian Transportation Agency on August first that HBR has begun soliciting contracting bids to repair the washed out tracks but the money is not there to cover the costs of the work.

A  report to the Canadian Transportation Agency (CTA), ordering HBR to start repairs by July 3 this year stated the process began with track inspection June 11 and June 12 by independent auditor AECOM. HBR prepared request proposals (RFP) and submitted them on June 28 to six pre-screened eligible contractors. Four of the six contractors attended a mandatory site visit on July 12 – 13. AECOM responded to technical questions form the contractors through July and bids were submitted and by August 3rd. AECOM stated it was “confident there will be multiple bids and methodologies to consider.”

Hudson Bay Railroad states that a substantial amount of repairs can be finished this year and then concluded by mid-2019. The goal is to restore limited service during this winter and then have full service soon after that when repairs conclude. Again, the report painstakingly reiterated facts that money was currently not available to initiate a definite repair plan.

“As the agency is aware HBR does not have the financial capability to undertake the full repairs of the damage to the railway caused by the spring 2017 flood,” Sabatini wrote. “HBR and its shareholders have been in discussion with the federal government and a potential buyer with the objective of ensuring that the necessary funds are in place to fully repair the Gillam to Churchill line and resume operations as expeditiously as possible.”

Pin It on Pinterest

Share This