by Steve Selden | Aug 20, 2017 | Churchill Photography

The Port of Churchill has been a symbol of uncertainty in Churchill. Katie de Meulles photo.
The uncertainty surrounding the Port of Churchill sale by owner Omnitrax from Colorado to a native alliance coupled with the natural destruction of the Hudson Bay Line has left Churchillians wondering the future of their town. This photo of the port captures the plight and the promise of the the time all in one image!
by Steve Selden | Jul 21, 2017 | Churchill News

Tracks have been washed out in multiple places between Churchill and Gillam. Mike Spence photo.
Omnitrax, owner and operator of the Hudson Bay Rail line is continuing to seek government and First Nation help to fix the only land access to Churchill. Estimates of $60 million would restore the tracks to operation by the end of October. However, Omnitrax says they can’t and won’t do it alone!
“It [the rail line] is not commercially viable, so we believe it’s a public utility,” said Peter Touesnard, chief commercial officer for Omnitrax.
“We believe it’s still the least expensive way to supply service to the north, in particularly the community of Churchill, and we believe there is a role for the public to play in that.”

Peter Touesnard, chief commercial officer for Omnitrax. Jaison Empson BBC photo.
Two March blizzards of epic proportions melted this spring into widespread flooding across the tundra from Gillam to Churchill. Water flows across the land since permafrost lies just beneath the surface and it does not percolate into the soil though. Instead, it flows across the land and when enough accumulates it can move with a powerful force destroying man made features in its path. The ensuing damage to the tracks between Gillam and Churchill have caused a storm of even greater proportions.
With the crucial lifeline to the town inoperable and the main shipping line for goods and supplies cut off, food prices have dramatically increased and businesses have been forced to lay off staff due to soaring costs of securing the goods for their business to operate.
A written statement from Omnitrax was released on Tuesday via a spokesperson for the office of Transport Minister Marc Garneau:
“Omnitrax has an obligation to repair and maintain its line and maintain service to residents, and we expect Omnitrax to meet its obligations,” the statement reads.
“If Omnitrax fails to meet its obligations, our Government will have to examine what are the next steps and alternatives to ensure residents can get the food and supplies they need.”
Omnitrax announced Tuesday morning, that the company has a 60-day plan starting in September to begin repairing the tracks contingent on securing contractors, housing and resources for the project
Churchill Mayor Mike Spence says the timeline for rebuilding portions of the track and replacing bridges and culverts is leaving very little wiggle room with regards to weather in the north.
“The end of October and that’s it, your construction season is done,” Spence said. “So we’re running out of time, here. Let’s get on with it.”

Churchill Mayor Mike Spence. Jaison Empson photo.
Provincial Infrastructure Minister Blaine Pedersen stated his dissatisfaction with the Omnitrax repair schedule and plan; “Today’s technical briefing provided by Omnitrax was clearly inadequate, leaving many unanswered and hypothetical questions.”
“Our senior provincial officials have repeatedly asked Omnitrax for details about their independent engineering assessment and future intentions of the rail line including timetables respecting necessary mitigation efforts, details of insurance policies and status of claims, to which we have had no response,” Pedersen said.
“What was made clear today by senior Omnitrax officials is that they are not prepared to repair, maintain or operate the rail line. It appears that they intend to abandon the line. If so then it is their obligation to the people of Churchill and indeed Manitobans to communicate their abandonment decision to the federal government.”
A third – party track assessment Omnitrax commissioned was completed by AECOM Canada and the engineering company identified 31 washout areas, 68 culverts and 13 bridges requiring repair over the 300 kilometer run of the track from Gillam to Churchill.
In June the Canadian government approved an extension for the Nutrition North food subsidy program so Churchill would be able to keep grocery prices at a somewhat affordable price until rail service resumes. With Manitoba Health also contributing to the subsidy effort the rate will be at $1.60/kg.
by Steve Selden | Jun 20, 2017 | Churchill News

One of the Hudson Bay Line’s washouts between Gillam and Churchill. Omnitrax photo.
Omnitrax does not have the resources to repair the Hudson Bay Railway and is urging the Canadian Government to get involved to help get the trains running again according to Merv Tweed, President of the company’s Canada management team.
“We’ve said publicly that we believe the province and the federal government have to be involved in this. It is a natural disaster,” Omnitrax Canada president Mervin Tweed said Friday.
Omnitrax is claiming there are at least 24 track sections between Gillam and Churchill, Manitoba that were severely damaged during the spring thaw and floods. Given the complexity of accessing the tracks and the permafrost base they lay on, the company is forecasting spring 2018 as the earliest time the repairs will be completed.

Flooding has caused some of the Hudson Bay Rail line to be underwater. Omnitrax photo.
Omnitrax has conducted aerial photo surveillance revealing long stretches of water submerged tracks, culverts displaced and suspended tracks above the ground with water running under them. This type of damage will be difficult to repair with expediency and forethought for future flood damage.
The Canadian government has not committed to any help before knowing what the costs will be.
“I mean, they’re being cautious. It’s hard to do something until you know — like us — what it’s going to cost,” said Tweed.
The Hudson Bay Railway is a lifeline between Churchill and the south. Trains typically bring up everything from fresh groceries to propane gas for heating homes. as well as building materials and anything else needed by residents and businesses. Without this service the economy and lifestyle in Churchill will be drastically affected.
The assessment, including 300 kilometers of tracks, 28 bridges and 600 culverts is beginning this week will take four weeks to analyze the tracks and two more to provide a comprehensive report detailing the process of repairing the line.
Tweed estimates the cost will be far larger than what Omnitrax can afford for the project.
“We don’t believe we have the resources to rebuild what needs to be done,” said Tweed. “Every time we go out we find something else.”
A difficult job ahead for engineers includes walking along the tracks and checking the stability of the line as well as taking soil samples in order to determine ground conditions under the tracks.
“Just getting to that site is going to be a real challenge,” Tweed said.
The tundra north of Gillam is saturated and many areas are covered with water slow to be absorbed by the permafrost – covered ground.
In the meantime, while the track is unusable north of Gillam, a plan to utilize both the Port of Churchill and the town’s airport is being assessed and put in place to cover the shipping deficiency.
Tweed stated that some port, owned by Omnitrax, employees have returned to work in preparation for aiding with additional shipments.
“We were optimistic about a pretty good rail season until the water hit,” Tweed said.
by Steve Selden | Jun 15, 2017 | Videos
The train crisis in Churchill is becoming a hot issue and Mayor Mike Pence has spoken out against the projection by track owner Omnitrax of a winter or even spring repair order and opening. A town meeting last night in Churchill drew nearly half of the 900 residents in town.This issue will be one we follow for the forseeable future as it has incredible impact on Churchillians and travelers hoping to visit for beluga whale and polar bear season. Stay tuned for updates on this developing story.
by Steve Selden | Jun 13, 2017 | Churchill News
Owner and operator Omnitrax has shut down the Hudson Bay Rail line for the forseeable future due to flooding causing destruction of the tracks. Estimates for reopening are now being projected as far out as next spring.
The “unprecedented and catastrophic” damage will take months to repair, said Peter Touesnard, chief commercial officer at OmniTrax, the Denver-based owner of the rail line that brings supplies into Churchill. “Until we are able to get people physically on the ground and do a proper inspection, it’s difficult for us to truly know [how long repairs will take],” Touesnard.stated.
The closure is also straining the local economy and workforce preparing for the summer beluga whale season. Businesses are being forced to consolidate their work staff as the number of tourists traveling to Churchill this summer will be drastically reduced. News of at least five layoffs so far has spread and more are expected soon with the official announcement of the rail line suspension.

Tundra Inn owner Belinda Fitzpatrick in front of her restaurant. Hannah Manczuk photo.
Belinda Fitzpatrick, owner of the Tundra Inn had to deliver the bad news to five workers last Saturday. “Quite heartbreaking,” said Fitzpatrick. “It was really upsetting.”
Plans for a seasonal restaurant at the Tundra Inn slated to open next week had to be put on the back burner. Other businesses are facing the same challenges as the the closure becomes a reality.
Fitzpatrick has been calling guests and seeing if they are able to fly to Churchill instead. However, cancellations have been coming in and she estimates she will lose a majority of travelers planning to stay at the inn and hostel.
OmniTrax is reporting unprecedented and catastrophic damage to the rail line caused by heavy flooding resulting from heavy snow pack left over from two massive March blizzards. The company says the track gravel bed has been washed out in 19 locations along the line. At least five bridges have visible damage and assessments of 600 culverts and around 30 more bridges will need to be examined for structural integrity.

Flooding in the Churchill area and south along the rail line have forced its closure. Ricci O’connor photo.
“While the Hudson Bay Railway requires significant seasonal maintenance, the extent of the damage created by flooding this year is by far the worst we have ever seen,” Touesnard said.
Fuel for the town is an especially critical commodity, and while the port could be used, at least during the ice-free season, winter will pose another extreme hurdle and potential emergency for all of Churchill.

Home Hardware in Churchill under stress from the rail line closure. Facebook photo.
Dale de Meulles and his wife Rhoda have run Churchill’s hardware and lumber store for the past 14 years and with the train out they will be unable to stock lumber and other building and home supplies sufficiently. Although competition in town is not there, they will have a tough time meeting expenses and payroll for 10 staff people without money coming in.
“We don’t know how we’re going to survive, to be honest,” said Rhoda de Meulles.
Dale de Meulles gives two months as a deadline for the layoffs. Last year’s Port of Churchill layoffs have already put pressure on the workforce in the town and the rail closure will continue that strife. Seasonal workers will also be hit hard without the tourism dollars coming in.
“We’re trying our best to keep them,” he said. “They gotta feed their families just like everybody else.”
“We’re just trying to survive.”
“As a Churchillian, we will never give up,” de Meulles said. “We’ve had so many hurdles in front of us and we keep jumping over them, but we need help this time.”